Production hall, Germany
Five electricians, twelve weeks: cable trays, sub-distribution, hall lighting with emergency lighting, test reports per board.
Electrical crews for building services and industry: cable trays, wiring, distribution, lighting and commissioning. Executed to the responsible planner’s specification, with test reports.
The hourly rate is 35 to 38 euros. Electrical work carries the strictest documentation: loop, insulation and RCD testing with a report are part of the service, not an extra line. If you do not ask for the paperwork, you still get it — it protects both sides.
Five electricians, twelve weeks: cable trays, sub-distribution, hall lighting with emergency lighting, test reports per board.
Three electricians, six weeks: floor boxes, presence detectors, lighting to the planner’s calculation.
Two electricians, four weeks: LED replacement during operation, in phases, without stopping production.
Each crew has a foreman with completed electrical training. Work on distribution boards follows the responsible planner’s specification and sign-off — responsibility for the installation stays with them.
We do, with calibrated instruments: insulation, loop and RCD tests, documented per board. You receive them at acceptance.
Yes, after approval and with a prior survey. What we find is documented with photos before we touch it.
Registration with the network operator and acceptance by the authority is handled by the licensed local contractor. We deliver the work and the paperwork for it.
Trade, location, period, headcount — reply within one working day.